New York University

Location: 5-11 University Place, New York, NY
Size: 250 Rooms
Construction Schedule: 12 wks
Architect: H&G Architects
Engineer: Lizardos Engineering 

L&K Partners was hired to renovate student resident rooms and to upgrade the HVAC and plumbing systems to NYU’s Weinstein Residence Hall.  The project required detailed planning as renovations at the residence occur only every 15 years.  

The construction window was 12 weeks between semesters.  With concise planning and implementation, L&K Partners procured all materials in advanced and renovated the entire building in time for the fall enrollment.

LIM College

Industry: Education
Location: 216 East 45th Street, New York, NY
Size: 70,000 square feet
Construction schedule: 14wks
Architect: Butler Rogers Baskett
Engineer: Simon Rodkin Consulting 

L&K was hired as the construction manager and general contractor to build out LIM’s new classroom campus and student centers across four separate buildings.  The project involved detailed planning to budget and establish constructability studies for each building.  Once the program was finalized, an aggressive construction schedule was established to allow the project to be completed during the summer months. 

The project was completed on time and within budget, and the new facilities opened concurrently at the start of the new school year.

Kaplan

Location: 888 Seventh Avenue, New York, NY
Size: 50,000 square feet
Construction Schedule: 20 weeks
Architect: Linea 3D
Engineer: CFS Engineering

Kaplan is a for-profit corporation specializing in higher education programs, professional training courses, test preparation materials and other services for various levels of education.  Constrained by a very tight building envelope, L&K worked with the design team to build out their executive conferencing center which consisted of meeting rooms, a café-style pantry and an auditorium. 

Through careful coordination of infrastructure and finishes, Kaplan’s Executive Training Center was completed within schedule and budget.

Anonymous Foundation

Anonymous Foundation

Client: Anonymous Foundation
Industry: Not-for-Profit
Location: 160 Fifth Avenue, New York, NY
Size: 46,000 square feet
Construction Schedule: 18 weeks
Architect: Ted Moudis Associates
Engineer: Robert Derector Associates

L&K Partners collaborated with a private foundation focused on advancing the frontiers of research in mathematics and the basic sciences. For this project, the client wanted to create a warm environment for their employees and visitors.

We partnered with the client and design team to procure and install locally sourced materials. Through extensive research and collaboration with the team, the final project was delivered on time and within budget